재건축위원회 2018 2/4분기 합동임원회 보고

  • Create by: KUMCGW

    [웨슬리홀 재건축 – 2018년도 1/4 분기 보고 이후]

    1. 건축가 Construction Documents Phase 도면(90%) 제출

    – 건축위원회의 검토

    – Structural Drawings (박상원 권사)

    – Mechanical & Plumbing Drawings (정원영 교우)

    – Electrical Drawings (조요성 장로)

    – 건축가 및 엔지니어와 회동하고 Review Comments 의논

    2. Geotechnical Report

    3. Trail Waiver 신청 (Lewinsville Road)

    – County 요구 사항

    – 시간 및 비용의 부담

    – John Foust (Dranesville District Supervisor) 면담

    4. County에 건축허가 도면 제출 (Building Permit Application)

    a. Site Plan (4/9)

    b. Building Permit Set (5/11)

    c. Building Permit Expeditor 고용

    5. 건설업자 선정

    – 건축가 추천 (6회사)

    – 토목 엔지니어 추천 (1회사)

    – KUMC 면담 (8회사)

    – Competitive Bid vs Negotiation (Competitive Bid for Subcontractors)

    6. 공사기간에 필요한 Storage 공간 확보를 위한Barn 수리공사 종료

    7. 앞으로 할 일

    – Building Bid Set 완료

    – 건설업자 1차 마감 (Short List)

    – Health Department 편지

    – Asbestos Inspection Certification

    – Third Party Inspector 선정

     