건축위원회 3/4분기 합동임원회 보고

  • Create by: KUMCGW

    건축위원회 보고
    (2018년도 3/4분기 합동임원회)

    10/27/2018

    [웨슬리홀 재건축 – 2018년도 2/4 분기 보고 이후]

    1. Construction Documents Phase 도면 – Bid Set완료

    2. Trail Waiver 면제신청 (Lewinsville Road) – 승인

    3. County에 건축허가 도면 제출 (Building Permit Application)

    – Site Plan Permit (대지)
    – Building Permit (건물 – 3차 제출)
    – County Site Work Bond Posting

    4. 건설업자 선정

    – 경쟁입찰 초청 (5회사)
    – Pre- Bid Conference (4회사)
    – 입찰 결과
    . Company A : $3,201,597
    . Company B : 3,288,948
    . Company C : 3,378,139
    . Company D : 3,414,500

    5. 교인설명회 (8/12)

    6. 교인 총회 (8/26)

    – “웨슬리홀 재건축 건축업자 선정 및 계약을 건축위원회에 위임한다.” – 찬성 97%

    7. 건축업자와 공사비 절약 협상 (Value Engineering)

    – VE 소위원회 구성
    – 현재 $250K – 300K 절약 예상
    – 도면 수정 필요

    8. 앞으로 할 일

    – 건축업자와의 계약
    – 건축허가 받음
    – 기공식

     