건축위원회 2019 1/4분기 보고

  • Create by: hwcho

    건축위원회 보고 (2019 년도 1/4 분기 합동임원회) 02/09/2019

    [웨슬리홀 재건축 – 2018 년도 4/4 분기 보고 (12/22/2018) 이후]

    1. 건축 허가
    – Trail Waiver 허가: 12/12/2018
    – Site Permit (대지) 허가: 01/07/2019
    – Building Permit (건물) 허가

    2. Asbestos Abatement
    – Survey 완료
    – Abatement Proposal (3)

    3. 웨슬리홀 재건축 일정
    – Project Schedule
    – Schedule of Value

    4. 교인설명회 (예정)

     